BurnUp / 'Landing Zone'

...

Primary audience: Stakeholders and team

Uses:

  • Can be used for a squad team but more likely for a fix Fix Version or Epic

  • Adjust assumptions about scope and throughput rate to see how this might effect the dates

  • Review history to see if throughput or scope have had any expected changes

...

  1. Toggle between count of Issues or Points (if you have done estimating)

  2. Select the date range - either manually here or with the slider

  3. Adjust the rate at which the scope line is flattened out.

    1. The projected scope is based on assumed adjustments to the historical rate and the rate of scope growth. Higher numbers will flatten out the projected scope. The number refers to the rate at which the scope projection is decreased by..

    2. There is a upper and lower scope increase to give you a range

  4. Adjust projected completion rate. This shows the range of completion rates, based on historical completion rate.

  5. The manual overide override enables you to make assumptions about throughput rate.. and it overrides the historically based rate in (4). You might use this if there is not yet any history for the fix version / epic

  6. Decide on what your 'Definition of Done' state is

  7. Use the slicers to select Project, Fix Version, Components or Labels. These filters in this section persist across all charts.

...

Purpose: See the mix of work being done by a squad or Swimlane team - showing Issue Type

Primary audience: Stakeholders and Product Owners

...

  1. Shows the number of stories that took x days (cycle time) to get across the state(s) selected in 2

  2. Select what you want to measure cycle time across

    1. e.g. how much time stories spent in development

  3. You can see one more more issue types

  4. Decide if you want to remove outliers

  5. Select data range

Image Added

Item

...

Ageing Detail

Purpose: Identify work that has become stuck or forgotten whilst in the selected state e.g. In progress or 'ready for deployment'

...

  1. Choose the state which you are interested in

  2. Narrow search by one of the slicers

  3. Y-axis shows the number of days that each item has been in that state

Image Added