  • Provide stakeholders with a realistic expectation prediction of when they can expect delivery of a release or project. 
  • Show that there are two key variables that determine the ‘Landing Zone’ for a project;  The The Scope and the completion Completion rate (aka velocity).
  • Engage the business by showing them that they have influence over the completion dates by adjusting scope.  

    • The chart is so clear that many clients use it to report up to the highest level stakeholders in the organisation. 

  • Protect the team from unrealistic expectations of what is possible.

...

  • Historical rates of completion of work and the increase in scope.
  • The likely forecast increases in completed work and scope - these cross-over to form 'the Landing Zone' .
    • From experience, the rate at which Scope continues to grow surprises most teams and stakeholders.

More information on the burn-up

...

FieldDescription
ProjectSelect the project from the drop down list
LabelsType ahead until you see the labels you want. You can choose multiple labels and delete, using the cross, those that you don't want.Begin entering text and select from the list of labels generated. Multiple labels may be added and/or deleted
VersionsSelect the version(s) you wantusing the check boxes to select specific versions or select All
SprintsSelect the sprint(s) in the same way
ComponentsSelect the component(s)
Mode 2 Filter'Mode 2 History' - enables you to adjust the query to return issues that have only recently been labelled or moved into a version (see below for more details
Date selection

You can choose either a range - e.g. the last 12 weeks.

Alternatively you can choose a fixed start date with either a fixed end date or with a rolling end date that is always 'today'

Issue TypesSelect which issue types you want returned
SaveEnter a name before saving
LoadHit 'Load' to go and get the data for your chart

...

FieldDescription
Data interval Select the frequency you want to sample the historical data - in days.
Date rangeChoose the start date of the chart. The end date will default to 'today' and roll forwards - unless you fix it with a specific date.
Done StatesDecide which states represent 'Done' for you your team. This will be used to work out the lower red throughput line.
Manual ThroughputYou may want to override the calculated historical throughput rate e.g. in the early stages of a project, before the team's throughput has stabilised. You can enter a value here of the number of effort points the team is expected to finish per interval (as set above).
Manual RangeUse this to set the spread of the forecast optimistic and pessimistic lines (if you have used the manual throughput rate). You can set the Standard Deviation manually, e.g. if you don't yet have enough history to calculate the SD. This number will then be used to draw the optimistic and pessimistic forecast lines.
Estimated SizeThe chart calculates average item size based on history and uses this for all unestimated items. You can override this with an estimated size.
Hide and apply chart settingsThis will do a reload based on your new chart settings - and then hide the data selection panel.
Hide settingsHides the panel without reloading the data.




FieldDescription
Throughput Settings

SampleChoose how much of the project history you want to include to calculate the mean throughput rate (velocity) '75%' will use the last 75% of sample interval velocities to calculate the mean.

OptimisticOptimistic will calculate the higher throughput rate, as a standard deviation from the mean. '15' will provide 0.15 standard deviations from the mean

PessimisticPessimistic will provide the lower throughput rate, also using standard deviations from the mean.
Scope Growth settings

SampleChoose how much of the project history you want to include to calculate the mean Scope growth rate '75%' will use the last 75% of sample interval velocities to calculate the mean.

Upper Determines the rate at which the rate of scope growth slows down. So, '10%' means that for each interval (set above), the rate of growth is reduced by 10%. The same is applied to subsequent intervals, until the rate of growth is 0%.

LowerAs above - however this determines the lower scope forecast. If this is set to 100% then it gives a straight line.

...

These are not saved to the database but are personnel preferences as a user is looking at a chartpersonal formatting preferences.



Show Count/EffortThis enables you to toggle between Toggles between showing the Count of the number of items or the total effort Effort - on the Y axis.
Show/Hide unestimated itemsToggles between showing/hiding the number of unestimated items in the backlog.
Show/Hide bugsToggles betweeen between showing/hiding the number of bugs in the scope backlog.
Hide Title dataHides the table that summarises what which settings were selected in the creating of the chart.
Data x days old - refresh In order to speed up this chart we cache the last saved version of it. This could have been several days earlier. Click this button to refresh the data in the chart.

...

This filter applies to: Components, Labels and Versions.

Mode 1 (default) - Items that meet the current search criteria on particular dates through the project's history.

Example:

In this case we show items in history that meet the 'current selection criteria'. So if they match the search criteria at each individual historical interval date. e.g. if you selected 'Label A' then it will show for previous dates in history the items that match 'Label A' on those dates. 

...