Provide stakeholders with a realistic expectation of when they can expect delivery of a release. The chart clearly shows that there are two key variables that determine the ‘Landing Zone’ for a project;  The Scope and the Throughput rate (velocity). Showing

By showing the business that how they can directly influence the delivery dates is a key part of engaging helps to engage them in collective responsibility for project deliverables. the collective accountability to deliver the 

From experience the rate at which Scope continues to grow is a real surprise for most teams - increasing awareness of this fundamental aspect of a project is key to influencing the outcomes. 

The chart is so simple to comprehend that many clients use it to report up to the highest level stakeholders in the organisation. 

...


Selecting the data 

Select the project, version(s) and component(s).  Decide which Issue types you want to include - and hit load.  

...