Use this chart to... 

  • xxHelp the team adjust its focus during a sprint and intervene if the sprint looks like it is going off track
  • Increase awareness of the story burndown
    • Most other burn-downs only show task burndown, meaning that the team might be unaware it is doing mini-waterfalls - where all the stories are completed on the last day of the sprint.
    • It is better to be completing stories regularly through the sprint

What the chart shows...

...

  • The burndown of tasks - typically measured in hours
  • The burndown of stories - measured in points 
  • Click on the blobs on the lines to drill down and see details of the tasks or stories

Setting up the chart

  • Decide on which  issue types to track
  • Select the states which represent 'in progress'Choose the sprint 
  • Select the work-items (normally story and task)