Use this chart to...
- See how good your team's estimating has been and whether it's worth trying to improve it.
- Good input for retrospectives, where you can focus on some of the outliers to understand the root cause for the correlation between
What the chart shows...
- The strength of the correlation between and work item size (typically measured in story points) and the time it takes to go across the selected number of 'In Progress' states.
- Where 1 means there is a very strong correlation and 0 means no correlation.
- Hover over the blob to see details of the item cycle time - click through to open the item
- Issues and bugs are shown in different colours
Setting up the chart
- Decide on which issue types to track. Probably the user stories as most teams don't estimate bugs,
- Select the states which represent 'in progress'